Sliplining
Rehabilitation of Large Diameter Sewers
Richard C. Turkopp, P.E., Technical Director
Hobas Pipe USA, Inc.,
Houston, TX
(281) 821-2200; rickt@hobaspipeusa.com
Abstract
Much of this nation’s infrastructure is very deteriorated and requires
significant updating in order to maintain service levels. Included in this widespread
need is the vast network of sanitary sewers. Since these pipelines are almost
exclusively underground, direct replacement by open cut methods would likely be
cost prohibitive as well as very disruptive to surface activities. For these
reasons, several in-place renewal techniques have been developed to
rehabilitate sewer lines with minimal excavation. One such method is lining the
existing host pipe with a new, factory-made, slightly smaller pipe. This
process is called sliplining.
Introduction
Sliplining is a semi-trenchless renewal method since access to the host pipe is
gained by excavating a pit above the existing line and removing the top half of
that pipe for a distance long enough to insert the new liner pipes. Prior to
lining the existing pipe, generally, any debris, sludge or other material that
may prevent passage of the liner pipe, must be removed. After lining, typically
laterals are reconnected by point excavation. Grouting of the residual annular
space to secure the liner position and improve resistance to external loads
normally completes the installation. Several different types of pipes are used
in sliplining including PVC, HDPE and fiberglass (primarily centrifugal cast
fiberglass reinforced polymer mortar, acronym CCFRPM).
Diameters and Joints
Each of the pipe material types is available in specific diameter ranges and
generally with one of two joint types; gasket-sealed bell-spigot (segmented
system) or fused ends (continuous system).
Pipe Material Diameters Joint / System Installation
PVC </= 54” Gasket-sealed /
Segmented Push-in
HDPE-Solid wall </= 54” Fused ends / Continuous Pull-in
HDPE-Profile wall </= 144” Gasket-sealed / Segmented Push-in
CCFRPM </= 102” Gasket-sealed / Segmented Push-in
Advantages
1) All of the joining systems can be leak-free, thereby stopping infiltration
and exfiltration.
2) All of the materials are highly corrosion resistant, so further internal
deterioration due to chemical attack is prevented.
3) Properly designed and installed, all of these systems provide structural
reinforcement and may restore full integrity or more.
4) Depending on pipe thickness and insertion clearance, full flow capacity
recovery can typically be achieved and, frequently, it can be increased because
of the excellent hydraulic characteristics of these pipes.
Manning’s “n” Pipe diameter
for equal flow
0.009 new 13% smaller vs. pipes with “n” = 0.013
0.011 slimed 13% smaller vs. pipes with “n” = 0.016
17% smaller vs. pipes with “n” = 0.018
Typical diameter reduction is 6” to 12”, depending on the pipe wall thickness and desired amount of clearance for insertion. Typical annulus size is +/-5% of the host pipe diameter. Examples:
Liner Type Liner Wall
t ID Reduction Flow Capacity
CCFRPM 2 to 3% dia. 10% Increased
PVC 3 to 4% dia. 12% Increased
HDPE-SW 4 to 5% dia. 14% Approx. Equal
HDPE-PW 6 to 8% dia. 19% Decreased
5) Only general cleaning to
remove debris, sludge, etc. that would prevent passage of the liner pipe is
required. No surface cleaning of the host to create a bond is necessary.
6) Insertion of segmented liner systems can almost always be done in “live”
flow without by-pass pumping, flow diversion or plugging. Fused (continuous)
systems can only be done in low flow conditions or with flow diversion, by-pass
or temporary plug.
7) Insertion pits for segmented systems can be small: slightly longer than the
pipe section length. Insertion pits for continuous (fused) systems must be
longer to enable bending the liner from the surface into the host sewer.
8) Insertion push or pull distances can be quite long provided that the host
pipes’ alignment is suitable (relatively “straight”). Longest single push known
to me is 5600 feet of CCFRPM 51” inserted into an existing 57” RCP. Maximum
insertion distances for profile wall and hollow pipes are less due to lower
push capacities.
9) Insertion of segmented systems can be very quick. Sustained installation
rates of 240 feet per hour have been achieved many times with CCFRPM pipes.
10) Sliplining is a very cost effective method of rehabilitation. In fact, many
times it is the least expensive of all renewal procedures. Installed costs have
been as low as $3 to $4 per diameter inch. Actual cost will depend on many
items including local labor rates, number of shafts required, pit requirements,
host line cleanliness, cover depth, surface restoration, etc.
Limitations
1) Sliplining is a semi-trenchless method. Access pits for insertion of the
liner pipes are required.
2) Passage of the liner pipes through curves or PI’s in the host line may
require short sections, fittings or excavation.
3) Reconnection of laterals typically requires a point excavation at the
lateral.
4) Sliplining requires that the diameter of the line be reduced. However, this
does not necessarily mean a loss of flow capacity. In fact, many times the flow
capacity will actually be increased after lining despite the reduction in
diameter.
Summary
Sliplining is a very cost effective, performance proven, semi-trenchless (some
excavation required) sewer renewal method that is available in most all
diameters by installing a new factory-made pipe into an existing line.
Sliplining has been used successfully for over 30 years to solve pipeline
problems such as severe corrosion, structural deterioration, leakage and poor
flow. Sliplining features minimal disruption and frequent live flow insertion
with out by-pass pumping or diversion. Several types of liner pipes are
available and all have been used successfully.
If you have any questions, please contact Dr. C.Vipulanandan
Copyright © 1998 University of Houston